Dennis Dean Road Paving & 7th and Fir Street Water Line Replacement
-
Paving is finished on Dennis Dean Road
-
Walk-through/punch list meeting has been done for paving and contractor to finish last few items on list
-
Lift station is done and operational
- Contractor currently working on 7th and Fir Street water line - majority of water line in
- Currently working on 7th and Elm corner / approximately 40' of pipe left to put in
- Filling, pressure testing, water testing to remain before doing service line hook-ups
- Fine grading will be done after service line hook-ups are finished
- All progress is weather dependent
30th & Furnas Street Water Line
- Water line is installed and finished
- Concrete has been re-poured in all removed areas
- All water service connections have been made
- Hydro-seeding has been done
- Fine grading and final walk-through remains